Australian Rural & Regional News reminds readers that a media release is a statement of the author given. Media releases vary widely in reliability and may contain a combination of fact, aspirational statements, opinion, political commentary and even error. Especially on contentious issues, we suggest our readers read widely and assess the statements made by different parties and form their own view.

Recent stories

This story is open for comment below.  Be involved, share your views. 

Murray–Darling Basin Authority, Media Release, 1 July 2026

In 2017, Basin governments agreed to a package of 36 projects in the southern Basin that would deliver environmental benefits equivalent to 605 gigalitres per year (GL/y) of recovered water. This allowed the sustainable diversion limits in the southern Basin to increase by 605 GL/y.

The BOC oversees the notification, amendment and withdrawal of these Sustainable Diversion Limit Adjustment Mechanism (SDLAM) projects.

Projects originally had to be completed by 30 June 2024, however, responding to calls from jurisdictions for more time, the Water Amendment (Restoring our Rivers) Act 2023 (Cth) extended the deadline to 31 December 2026 and enabled three new projects to be included.

Of the 39 notified SDLAM projects, 13 have been completed and are already delivering Basin Plan outcomes. An additional 10 will be delivered on time and will also be included in the SDLAM reconciliation.

Due to a range of implementation challenges for these complex projects, 14 projects will not be in operation by the deadline of 31 December 2026 and therefore have been necessarily withdrawn from the SDLAM as supply measures by the BOC. While this includes 4 projects that are also supporting constraints relaxation, funding for these constraints projects will continue through to 2027 as contracted, to enable continuation of current constraints measures.

Some of these projects still have the potential to provide environmental benefits in the Basin and may be considered in the future.

Following consideration by the BOC, the Murray-Darling Basin Authority (MDBA) will finalise the SDLAM reconciliation in late 2026 to determine the final supply contribution from the completed projects and the shortfall against the 605 GL/yr offset.

The shortfall, and lessons for future programs, will be considered by Basin ministers in the context of the Basin Plan Review.

In addition, at the virtual BOC meeting on Thursday 4 June, the Basin Community Committee (BCC) Chair provided an update on recent BCC meetings, and recent themes emerging from community consultations. The Committee noted an update on the recruitment process for a replacement First Nations member to the BCC which will be formalised with the Murray–Darling Basin Ministerial Council (Ministerial Council).

The BOC heard from the Murray–Darling Basin Authority Chief Executive on the upcoming priorities for the Basin Plan Review, following the Basin Plan Review Discussion paper submission close date of 1 May 2026. Members heard the key themes that were emerging from recent consultation activities and received advice on next steps for the review.

Members received a progress update on the Statutory Review of the Role of the Inspector-General of Water Compliance (IGWC), noting the final report will be provided to the Commonwealth Minister by 30 June 2026.

The Committee met with Vanessa O’Keefe, recently appointed as the Deputy Reviewer of the review of the Water Act 2007 (Cth), and noted upcoming consultation with First Nations stakeholders across Australia, including in the Basin.

BOC also discussed the development of the Joint Programs multi-year budget and workplan.

BOC will next meet in August 2026.

Summary of SDLAM measures

  • 23 measures will be operational by 31 December 2026
  • 14 measures are withdrawn
Measure NumberNotified MeasureProject Status/key issues
1South East Flows Restoration Project (SEFRP) – SAIn operation
2Flows for the future (Eastern Mt Lofty Ranges) – SAIn progress and amended
3South Australian Riverland Floodplain Integrated Infrastructure Program (SARFIIP) – SAIn operation
4Riverine Recovery Project (RRP) – SAIn operation
5Chowilla Floodplain The Living Murray project (TLM) – SA/NSW/VICIn operation
6South Australian Murray Key Focus Area – SA (Constraints)In operation
7Lindsay Island (Stage 1) Upper Lindsay watercourse enhancement TLM Project – VIC/NSW/SAIn operation
9Mulcra Island Environmental Flows TLM Project – VIC/NSW/SAIn operation
10SDL Offsets in the Lower Murray (Locks 8 and 9) – NSWIn progress and amended
12Hattah Lakes North Floodplain Management Project – VICIn progress and amended
13Hattah Lakes TLM Project – VIC/NSW/SAIn operation
16Vinifera Floodplain Management Project – VICIn progress and amended
19Murray and Murrumbidgee Valley National Parks SDL Adjustment – NSWIn progress and amended
20Gunbower Forest TLM Project – VIC/NSW/SAIn operation
22Flexible Rates of Fall in River Levels Downstream of Hume Dam – VIC/NSWIn operation
24Barmah-Millewa Forest Environmental Water Allocation – VIC/NSWIn operation
29Hume Dam airspace management and pre-release rules – NSW/VICIn operation
30RMIF: 2011 Snowy Water Licence Schedule 4 Amendments to River Murray Increased Flows Call Out Provisions – NSW/VICIn progress and amended
32Nimmie Caira Infrastructure Modifications – NSWIn operation
33Yanco Creek: Modernising Supply Systems for Effluent Creeks Murrumbidgee River – NSWIn progress and amended
35Computer Aided River Management (CARM) Murrumbidgee – NSWIn progress and amended
40Restoring Murray Waterways – NSWIn progress and amended
41Restoring Flows to the Mallee Floodplain – VICIn progress and amended
8Lindsay Island Floodplain Management Project – VICWithdrawn
11Wallpolla Island Floodplain Management Project – VICWithdrawn
14Belsar-Yungera Floodplain Management Project – VICWithdrawn
15Burra Creek Floodplain Management Project – VICWithdrawn
18Guttrum and Benwell State Forests Floodplain Environmental Works – VicWithdrawn
21Gunbower National Park Floodplain Management – VICWithdrawn
26Yarrawonga to Wakool junction Key Focus Area – NSWWithdrawn
27Improved Regulation of the River Murray IRORM – VIC/NSWWithdrawn
28Hume to Yarrawonga Constraints Key Focus Area – NSW/VICWithdrawn
31Enhanced Environmental Water Delivery (EEWD) – NSW/VIC/SAWithdrawn
34Improved Flow Management Works at the Murrumbidgee River – Yanco Creek Offtake – NSWWithdrawn
36Murrumbidgee Key Focus Area – NSWWithdrawn
37Structural and operational changes at Menindee Lakes includes Lower Darling KFA – NSWWithdrawn
42Murrumbidgee Airspace Management – NSWWithdrawn

Related story: Labor dumps Basin water projects in favour of more buybacks: McCormack

, , , , ,

KEEP IN TOUCH

Sign up for updates from Australian Rural & Regional News

Manage your subscription

We don’t spam! Read our privacy policy for more info.

Subscribe for notice of every post

If you are really keen and would like an email about every post from ARR.News as soon as it is published, sign up here:

Email me posts ?

Enter your email address to receive notifications of new posts by email.

Share your views

Australian Rural & Regional News is opening media releases for comment to encourage healthy discussion and debate on issues relevant to our readers and to rural and regional Australia. Defamatory, unlawful, offensive or inappropriate comments will not be allowed.

Leave a Reply